5.3.2.5 IfcTaskTypeEnum
5.3.2.5.1 Semantic definition
The IfcTaskTypeEnum defines the range of different types of task that can be specified.
5.3.2.5.2 Type values
Type
Description
ADJUSTMENT
Making changes to the physical configuration of something.
ATTENDANCE
Attendance or waiting on other things happening.
CALIBRATION
Making changes to the operational configuration of something.
CONSTRUCTION
Constructing or building something.
DEMOLITION
Demolishing or breaking down something.
DISMANTLE
Taking something apart carefully so that it can be recycled or reused.
DISPOSAL
Disposing or getting rid of something.
EMERGENCY
Tasks required when responding to, or ensuring the ability to respond to, an emergency situation.
EXAMPLE Spaces, zones, and systems may have emergency tasks in the case of different emergency conditions.EXAMPLE A task to ensuring the safe configuration of an equipment during an unexpected situation.
INSPECTION
Check if something is installed and is operating within expected parameters.
INSTALLATION
Installing something (equivalent to construction but more commonly used for engineering tasks).
LOGISTIC
Transportation or delivery of something.
MAINTENANCE
Tasks required to keep an object in good working order.
MOVE
Moving things from one place to another.
OPERATION
A procedure undertaken to start up the operation an artifact.
REMOVAL
Removal of an item from use and taking it from its place of use.
RENOVATION
Bringing something to an 'as-new' state.
SAFETY
Tasks required to ensure safe use of the object. For example electrical 'lock-out' instructions.
SHUTDOWN
The set of tasks required for an orderly shut down without adverse impacts, typically applied to systems.
STARTUP
The set of tasks required to begin or restart operation without adverse impacts, typically applied to systems.
TESTING
The set of tasks required to evaluate the performance of an object, to ensure if something is installed and is operating within expected parameters.
EXAMPLE A system or element type may have testing tasks as part of routine maintenance.
TROUBLESHOOTING
The set of tasks required to diagnose commonly encountered performance problems, typically applied to element types and systems.
USERDEFINED
User defined.
NOTDEFINED
Undefined.
Table A
5.3.2.5.3 Formal representation
TYPE IfcTaskTypeEnum = ENUMERATION OF
( ADJUSTMENT
, ATTENDANCE
, CALIBRATION
, CONSTRUCTION
, DEMOLITION
, DISMANTLE
, DISPOSAL
, EMERGENCY
, INSPECTION
, INSTALLATION
, LOGISTIC
, MAINTENANCE
, MOVE
, OPERATION
, REMOVAL
, RENOVATION
, SAFETY
, SHUTDOWN
, STARTUP
, TESTING
, TROUBLESHOOTING
, USERDEFINED
, NOTDEFINED ) ;
END_TYPE ;
5.3.2.5.4 References